s-curve doesnt show reality

Ferhat AciciMember for 13 years 10 months
Created
4
3
0

hi guys first of all sorry for my bad english i hope u understand.

in my schedule i have more than 2000 activities.i added wbs summary activity for each wbs.then i assigned budgeted (contrac price) and actual cost.some activities finished and some activities still on going.but i couldnt get s-curve how i want.s curve is here.whts the problem how can i solve this.please help

 

 

 

 

4 replies

Oldest first
  1. 0
    Manochehr Hosseini ·

    What version of P6 are you

    What version of P6 are you using? I had similar problem when I was using P6 6.2, after I switched to version 7 it was solved.

  2. 0
    Chris Rymer ·

    Hi Ferhat Have a look at

    Hi Ferhat

     

    Have a look at Project Tracker, it creates S curves directly from P6 without the need to export the data to a spreadsheet. You can get a free trial and more product infromation at www.willmer.co.uk

  3. 0
    Ferhat Acici ·

    hi all i m using 6.0 version

    hi all i m using 6.0 version of primavera.
  4. 0
    Manochehr Hosseini ·

    Can you send the XER file to

    Can you send the XER file to my email m.hosseini@yahoo.com

    I will check on another version and will let you know the outcome. 