why my Baseline & Actual units showing different after assigning the current project as a baseline ?

Irfan KhanMember for 17 years 3 months
Created
3
2
0

dear all,

i encountered with the problem which seems something unrealistic : means u update my schedule & than i made a copy the current schedule as a my baseline.

here when i am looking @ my units its showing different for past month. whereas it should be the same asplanned.

please check the attachment for reference.

thanks…... 

3 replies

Oldest first
  1. 0
    Charlie Daniels ·

    HI Irfan, Not sure that this

    HI Irfan,

     

    Not sure that this will help, I had a similar problem recently.

    If I looked on the Gantt Chart the Baseline Bar didn't line up with the current bar.

    The dates were not lining up either. (I also created a new baseline using the current project)

    I checked the following:

    1. The correct Baseline was assigned

    2. The correct Columns were being displayed (relevant to that baseline)

    3. The correct baseline bars were selected on the Gantt Chart

    After all these were confirmed and correct it still dodn't match.

    I aligned the original duration with the remaining duration using global change, this seemed to have sorted the problem out.

     

    I hope this can help with your issue?

     

    Regards

    Charlie

  2. 0
    Ravi Katare ·

    Hi,Run GC to replace Planned

    Hi,

    Run GC to replace Planned start & finsh with start & finsh.

    - Ravi

  3. 0
    Gary Whitehead ·

    ...or just correct your

    ...or just correct your Primavera settings so it doesn't look at planned dates.

     

    http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf