Performance Performance didnt roll up as Per the Estimated Weight ????

Anas BabarMember for 12 years 8 months
Created
4
2
0

Hi guys,

Im a newbie to this site..


I’m facing mentioning problem regarding Est. Weight in P6.7.

I got Two WBS in Which WBS 1 having a weight age of 6.2 & WBS 2 having a weigtage of 3.8.
That means if I completed my First WBS (2nd WBS’s activities not started) my overall percentage complete should be 62%.

I assigned proper weightage to all the activities , but it didn"t rolled up WBS summary performance % as well..

The problem is After finishing WBS 1 my Overall % shown as 57.89% instead of 62% .How to recover this issue.??

How to assign Est Weightage that overall % accurately roll up in WBS & Project level .???

Guys got any thoughts???
Thanks in advance

4 replies

Oldest first
  1. 0
    Bong Yagahon ·

    Same problem with me here..

    Same problem with me here.. haiss,..appreciate very much to anyone who can provide light on this particular P6 issue.. Thanks.

  2. 0
    Bong Yagahon ·

    ..............

    ..............

  3. 0
    Bong Yagahon ·

    --------------

    --------------

  4. 0
    Rafael Davila ·

    I do not use P6 but with a

    I do not use P6 but with a few formulas or global changes plus a script it shall be easy to do with your software.

    http://www.youtube.com/watch?v=-hyTDRBK7v8

     photo 1-26-20147-57-46PM_zps3dc0f827.jpg

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?