Facing problems with comparing between baseline and Updated one

Hossam EwedaMember for 12 years 8 months
Created
6
5
0

Dear All,

I need your help 

Why 

1> when i assigned baseline with the updated Sch. i found the percent on (performance % complete) column changed

from 41.06 % to 40.92

2> How i could compare between base line and the updated 

when i showed (planned value, actual value, remainig value, budget value) not right values like example 

remaning value + actual value        Not equal     Budget total cost

and planned or Scheduled vlue -  Actual value       Not equal   variance value 

3> and why actual cost column give me value equal zero although    performance % complete equal 41.06% 

 

thank you for help

6 replies

Oldest first
  1. 0
    AB Timo ·

    untitled.png

  2. 0
    Hossam Eweda ·

    Dear AB TimoThank you for

    Dear AB Timo

    Thank you for trying but i tried that it not working

    Still Actual cost zero for all items

    still remaning plus actual not equal budget

    about changing performance % from 41.06 to 40.92 after assiging baseline it solved when i assign baseline just on the project baseline not in primary one

    but i still facing the 1st problem

     

  3. 0
    AB Timo ·

    HossamIf you have not checked

    Hossam

    If you have not checked auto-compute actual box,then cost will not be filled according to % Complete.

    you need to enter actual cost in actual cost column or if you want primavera to compute based on % complete then you need to check auto-compute actual then Run "Recalculate the assignment cost"

    May be it will solve the problem

  4. 0
    Hossam Eweda ·

    i found PF = .88    not equal

    i found PF = .88    not equal (1) i think it ought to be (1) 

    to give me the right equation 

    budget - remaning = actual 

    but when i changed it no new action and no change on the value of remaning still same number 

     

    Still the main Problem with me that Actual cost for some items not calculating atuomaticaly.

  5. 0
    Hossam Eweda ·

    Dear i am realy grateful for

    Dear i am realy grateful for your interest

     i am already checked that box for item i know it has a problem for calculating 

    and i am sure that all items already marked as auto copmute 

    and i made Recalculate the assignment cost"   from tools 

    but it still not working

  6. 0
    Hossam Eweda ·

    Dear All I found the

    Dear All 

    I found the respone 

    You need to use (Apply actual ) from tools after every update to calculate the actual cost from your updated percents

    but notice that step no undo for it you cant come back with data date, for that you need to make export first for your project. 