Activity % complete and Schedule % complete

Vrinda MMember for 18 years 4 months
Created
2
2
0

Dear all,

 

Please help urgently as I have program in P6 which needs to be updated weekly.

But from last 2 weeks Iam updating the program in P6 howver the activity % complete is not changing and schedule % complete is changing and showing increase.However the Activity % is not showing any change,.

 

What could be the reason for this???

 

Rgds,

Vrinda

0507641002

2 replies

Oldest first
  1. 0
    walid Lahiani ·

    Good morning,I looked for

    Good morning,

    I looked for your question,I found in the net that:

    There are many different methods for calculation of actual progress in Primavera P6.  These methods involve using many fields and settings, including:

    • Duration % Complete
    • Units % Complete
    • Physical % Complete
    • Percent Complete Type
    • Activity % Complete
    • Performance % Complete
    • Earned Value settings of the WBS Elements

    So may be you are showing in your column an other percent complete different of the percent complete of your global project

     

    Good luck

  2. 0
    Neeraj kumar ·

    Dear Vrinda, Activity

    Dear Vrinda,
     
    Activity percentage completion type is "Duration" in your project. You shall change the "Type" among Duration-Units-Physical.
    1. Choose Project, Activities.

    2. Select the activity whose percent complete type you want to define.

    3. Display Activity Details, then click the General tab.

    4. Select the percent complete type:

      To indicate that the activity's percent complete will be entered by the user for this activity, select Physical. In this case, Activity % Complete = Physical % Complete.

      To specify that the activity's percent complete be calculated from the original or planned and remaining durations, select Duration. In this case, Activity % Complete = Duration % Complete = (Original or Planned Duration – Remaining Duration) ¸ Original or Planned Duration.

      To specify that the activity's percent complete be calculated from the actual and remaining units, select Units. In this case, Activity % Complete = Units % Complete = (Actual Labor Units + Actual Nonlabor Units) ¸ (Actual Labor Units + Actual Nonlabor Units +Remaining Labor Units + Remaining Nonlabor Units).