Budgeted units unable to edit

Parthiban SekarMember for 13 years 8 months
Created
5
21
0

I couldn't able to edit Budgeted units or Remaining units in Resource assignments window. However same can be done in Resource usage spreadsheet. Why? How to overcome this?

I logged in with full rights (both admin superuser & project superuser). I used only "Fixed Duration & units" as duration type.

Can somebody help? Thanks.

5 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Probably a good idea to tell

    Probably a good idea to tell us what software you are using....

  2. 0
    David Craig ·

    Perhaps if you change it to

    Perhaps if you change it to just fixed duration, then you may be able to edit the units?

    You can then change back to fixed duration and units once you have edited the units.

  3. 0
    Parthiban Sekar ·

    The software used is

    The software used is Primavera P6R8.3.

    Hi David,

    Usually with fixed duration & units also it is possible to manually edit the budgeted units in Resource assignments window. (this is future period bucket planning as I understood)

    and there is no duration type like fixed duration in Primavera

     

  4. 0
    Gary Whitehead ·

    Moved to Primavera Forum

    Moved to Primavera Forum

  5. 0
    Parthiban Sekar ·

    Hi there, anybody who could

    Hi there, anybody who could help on this? I really appreciate it.