Layout

Muhammad SaqibMember for 12 years 9 months
Created
1
2
0

When some layouts are already saved in P6. After importing some baseline as well as updated and on assigning that layout gant chart is showing emptry. so what is the successful solution to apply that layout

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    If gant chant is showing

    If gant chant is showing empty, is it because a filter has been saved as part of the layout, that is returning zero activities.

     

    So either the filter in layout is wrong, or the project does not have the right codes for the filters to work.

     

    Either way: check your filter