Skip to content

Linking activities based on physical % complete

Haroon RasheedMember for 18 years
Created
3
4
0

Hello evereyone,

Is there any method by which one can link an activity based on the predecessor's physical % complete in Primavera P6?

Linking SS or FS - is not serving the purpose.

Thanks in advance.

Haroon

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Nope. One of Primavera's

    Nope.

     

    One of Primavera's major failings, this.

     

    The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete.

     

    Other alternative is to split the predecesor activity into 2, and use FS links

  2. 0
    Haroon Rasheed ·

    Hello Gary,Thanks for the

    Hello Gary,

    Thanks for the response.

    Are you aware of any other software that can do it?

     

    Haroon

  3. 0
    Gary Whitehead ·

    Asta and Spider both have

    Asta and Spider both have this facility.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?