Linking activities based on physical % complete

Haroon RasheedMember for 18 years
Created
3
16
0

Hello evereyone,

Is there any method by which one can link an activity based on the predecessor's physical % complete in Primavera P6?

Linking SS or FS - is not serving the purpose.

Thanks in advance.

Haroon

3 replies

Oldest first
  1. 0
    Gary Whitehead ·

    Nope. One of Primavera's

    Nope.

     

    One of Primavera's major failings, this.

     

    The best you can do is SS+lag, with the lag representing the estimated time required to achieve the desired % complete.

     

    Other alternative is to split the predecesor activity into 2, and use FS links

  2. 0
    Haroon Rasheed ·

    Hello Gary,Thanks for the

    Hello Gary,

    Thanks for the response.

    Are you aware of any other software that can do it?

     

    Haroon

  3. 0
    Gary Whitehead ·

    Asta and Spider both have

    Asta and Spider both have this facility.