s-curve problem

Ferhat AciciMember for 13 years 10 months
Created
2
1
0

Hi Guys,

i have a problem with s-curve of my project regarding actual and budgeted cost curve.datadate is may 10,2014 i did not understand why budgeted and actual cost's curve are not same curve before datadate.i entered budgeted and actual cost manual.i can send xer file.sorry for my english.i hope i could tell my problem.

2 replies

Oldest first
  1. 0
    SH. Abi ·

    Hi Ferhat,         As I

    Hi Ferhat,

     

          As I understood, you wondering why the actual cost before the data date is not matching with the budgeted cost , well thats because the distribution of the cost before the data date is changing with keeping the latest cumulative cost correctly. anyway, you can send me the file on abdallasaid@hotmail.com to check it if you want.

     

     

    Regards,

    Abdallah  

  2. 0
    Ferhat Acici ·

    thank you Dear Abdallah.i

    thank you Dear Abdallah.i sent it 

Log in or join to reply