budgeted unit problem

Ferhat AciciMember for 13 years 10 months
Created
2
3
0

Hi Guys,

i assigned a labor resource which has 10/d default unit time and 40/d max unit time ( for 4 labours),and activity has 5 days duration.according to my calculation 40*5 = 200 (budgeted unit).but primavera says budgeted unit is 50 (5*10).whats the problem?

2 replies

Oldest first
  1. 0
    Gary Whitehead ·

    it budgets at the default

    it budgets at the default unit/time, not the max

  2. 0
    Ferhat Acici ·

    Thnk u Gary

    Thnk u Gary