budgeted unit problem
In the Open Standard
Ferhat AciciMember for 13 years 10 months
- Created
- 2
- 3
0
Hi Guys,
i assigned a labor resource which has 10/d default unit time and 40/d max unit time ( for 4 labours),and activity has 5 days duration.according to my calculation 40*5 = 200 (budgeted unit).but primavera says budgeted unit is 50 (5*10).whats the problem?
2 replies
Oldest firstLog in or join to reply