SCHEDULE HEALTH-CHECK

Neda NejadMember for 13 years 4 months
Created
4
5
0

Hi Folks,

 

Doesn any one know how to run schedule health-check after updating schedule for %complete/atcual cost on a weekly basis in EPC and FEED?

 

Neda

4 replies

Oldest first
  1. 0
    Neda Nejad ·

    Tom tx for ur email I sent u

    Tom tx for ur email I sent u a dummy email so that u can come to me with ur materials.

    Larry TX for ur help I am on P6.

  2. 0
    Neda Nejad ·

    Hi Tom TX for ur docs. they

    Hi

     

    Tom TX for ur docs. they are really invaluable!

  3. 0
    Zoltan Palffy ·

    The (DCMA) Defense Contract

    The (DCMA) Defense Contract Management Agency has a guide line that they have called a DCMA 14 Point Schedule Assessment. This 14 point check  is used to determing the overall quality and performance of the cpm schedule.

    listed below is the link to the DCMA documentation

     

    http://www.dcma.mil/policy/200-1/PAM-200-1.pdf

    https://www.plannertuts.com/dcma-14-point-schedule-assessment/

    There is also a free add on tool for excel called xertool kit. This uses and existing xer file to help gather the stastics to perform the elements of the 14 point assessment. Here is the link

    http://www.xertoolkit.co.uk/#All

  4. 0
    Neda Nejad ·

    Hi Zoltan, TX alot for the

    Hi Zoltan,

     

    TX alot for the links very helpful.