Query regarding how to choose EPS for a particular situation

Bindu Devi ReddyMember for 12 years 4 months
Created
5
3
0

Hello Everyone,

 I just know the basics of Primavera and trying to figure out what could be the best for the below described situation.

 The engineering group does the design of Y product. That Y product has three sub products say Y1, Y2 and Y3. And there are three different groups that has engineers to deal with respective products. And there are some 100 projects the engineering group as a whole is dealing with.

So my question is, is it better to create a one single while with all the projects in it or to create separate projects? Because if I create as seperate projects, would it be possible for me to track the schedule in future for the individual engineering sub groups? Does EPS any way help with this situation of mine.

Please lemme know if anyone has faced this situation and how you handled it.

Thanks

5 replies

Oldest first
  1. 0
    Bindu Devi Reddy ·

    Thanks Dieter. yeah all the

     

    Thanks Dieter.

    yeah all the projects have their own budgets but same user using all the projects. So I guess choosing different EPS would help me in this situation.

    Also I have one more question, is it possible to use primavera for a project where none of the activities are related to each other? I mean all the activities in the project are independent, they have no relationships. Is it worth while to use p6 for this type of project. It is not a constuction project.

     

    Thanks

    Bindu

  2. 0
    Bindu Devi Reddy ·

    Thanks Dieter. yeah all the

    Thanks Dieter.

    yeah all the projects have their own budgets but same user using all the projects. So I guess choosing different EPS would help me in this situation.

    Also I have one more question, is it possible to use primavera for a project where none of the activities are related to each other? I mean all the activities in the project are independent, they have no relationships. Is it worth while to use p6 for this type of project. It is not a constuction project.

     

    Thanks

    Bindu

  3. 0
    Dieter Wambach ·

    Bindu The EPS can be compared

    Bindu

    The EPS can be compared with a rack or a board with several locks. Along the EPS you assign access rights and budget.

    - How is the budget distributed - if you'll integrate them into Primavera?

    - Access rights: If you have a right for one node, you'll have this right for all nodes BELOW as well.

    - Avoid chaos: If you put paper into a binder you'll keep a certain structure to find it again.

     

    Hope tis may help.

    Dieter

  4. 0
    Dieter Wambach ·

    Bindu, sorry I made a mistake

    Bindu,

    sorry I made a mistake in my response - I corrected it meanwhile: If you have specific access rights for one EPS node, then you'll have them for all nodes BELOW as well.

    But for you only the consideration of budget will be relevant. In a normal company the budget is distributed:

    Area --> Goup of projects --> Project --> Part of a project (deliverable) with different names and/or different number of levels. Exactly this situation you can reflect in Primavera and run the activities against it.

    With more projects an EPS will be helpful in any case.

    Good luck!

    Dieter

  5. 0
    Dieter Wambach ·

    Bindu to your other

    Bindu

    to your other question:

    P6 will put the start of all activities onto the data date and they will run in parallel. Does this make sense?

    Regards

    Dieter