Need Help Creating a Filter between Schedule Updates for Delayed Critical Path Activities
In the Open Standard
Chris JenkinsMember for 12 years 1 month
- Created
- 3
- 2
0
Hello,
I am struggling to create a filter required by my owner between updates- below are the requirements:
"Activities within 14 calendar days of the critical path that were planned to occur during the updated period, but which did not occur or occurred later than the scheduled late start or late finish date, shall be identified and accompanied with an explanation for those delays."
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?