Open Ended Milestones

Haroon RasheedMember for 18 years
Created
9
4
0

Hello,

Can Monitoring Milestones like "Receive all Equipment", "Finish all MEP works" be kept open-ended if it does not have any single logical successor?

if otherwise, lot of float is generated (calculated upto project end).

How do you deal with this?

 

-Haroon

9 replies

Oldest first
  1. 0
    Dieter Wambach ·

    Hi Haroon (Hārūn

    Hi Haroon (Hārūn ar-Raschīd?)

    Before you start your planning you write down all assumptions and discuss them with the PM. The use of open end control milestones for reporting purpose in my opinion is absolutely but must be part of this discussion and part of the planning procedure. Otherwise this might lead to misunderstandings.

    Have a good planning

    Dieter 

  2. 0
    Haroon Rasheed ·

    Hello Dieter,I will state it

    Hello Dieter,

    I will state it on the "Basis of Schedule/Schedule Assumptions" document.

    Thank you for validating this method. I was worried if this was a taboo since everybody goes by the 'no-open-ends-except-first-and-last-activity' logic.

    Haroon

     

    P.S: yes, the same Haroon Al Rasheed ;)

  3. 0
    Vladimir Liberzon ·

    If somebody will insist on No

    If somebody will insist on No open ends link all open end milestones with project finish milestone.

  4. 0
    Haroon Rasheed ·

    Hi Vladimir,Linking like that

    Hi Vladimir,

    Linking like that will again generate huge Total float.

     

    Haroon

  5. 0
    Vladimir Liberzon ·

    Open ended activities in any

    Open ended activities in any case have huge total floats. They may be delayed up to project finish, so linking them with finish milestone does not increase their floats.

  6. 0
    Haroon Rasheed ·

    Hi Vladimir,I forgot to

    Hi Vladimir,

    I forgot to mention that you should tick the "Make open-ended activities critical" under Schedule options.

     

    -Haroon

  7. 0
    Mike Testro ·

    Hi HaroonIf the "monitoring

    Hi Haroon

    If the "monitoring milestones" such as "receive all euipment" are not linked to something in the programme then are pointless unless they are just in place for reporting purposes or to trigger some sort of stage payment.

    In which case any float is irelevant.

    Best regards

    Mike Testro

  8. 0
    Dieter Wambach ·

    Hi Haroon This setting does

    Hi Haroon

    This setting does only mean that if you'll filter for critical activities they'll be included to remind you to link them.

    In your case this link is - as Mike wrote before - irrelevant. I wouldn't mark this option.

    Regards

    Dieter

  9. 0
    Ahmed Aziz ·

    Hi Haroon,You have one of two

    Hi Haroon,

    You have one of two options:

    1- assign a constrain on the activity to finish on/ afte/ before a certain given date

    2- Link this activity to the final milestone of the project (for example finish project)

    Regards

    Aziz