integrating sub contractor schedule and Contractor schedule
- Created
- 9
- 5
Hi All,
In our project we have different sub contractors, providng their schedules to update the master schedule. In the beginning, the sub contractor schedule(without resources) was added to the our master schedule. Then I added the resources in our master schedule to make it as the baseline programme-and approved by the Client.
Now during the updating of our schedule, I was trying to incorporate the updated schedule(without resources) of sub contractor in our schedule, by importing it. The problem is that , as the sub cont schedule is without resources, during updating, our resource (budgeted units/cost) in the schedule is also changing. The start & finish dates are getting updated properly.
How to keep the resources(budgeted units/cost) in my schedule as it is, while importing the sub cont schedule with out resources?
Thanks in advance
Kannan
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?