Importing an xer filefrom V7 to V8, resources are missing.....anyone know the answer?
In the Open Standard
Doyin McarthurMember for 23 years
- Created
- 1
- 2
0
I have just upgraded to P6.8.2 however our contractor is using P6.v7, when they send me an xer file and I import this I show only about a quarter of the resources that they have. I have tried importing by insert new and also update resources but no difference.
Does anyone know how to solve this issue?
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?