Dears,

When you are using FF relationship, Do you use the minus Lag or not, like Activity B FF after Activity A Minus 10 days, if using minus log, will it working correct or not?

Thanks for your reply

Jason

6 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi JasonNever ever use a FF

    Hi Jason

    Never ever use a FF Lag in a construction programme

    Just because the software allows you to do it there is no situation in the construction process that is represented by a FF Link.

    Only ever use FS links.

    If you a putting in a SS link with a lag you are really using a FS link except that you are guessing where the finish point is.

    Best regards

    Mike Testro

  2. 0
    Jason LI ·

    Thanks Mike, If only think

    Thanks Mike,

    If only think it from the soft wise, and not consider the construction step, why P6 Provide the FF relation, and when we can use the FF relation actually.

     

    Best regards,

    Jason.

  3. 0
    Jerome Odeh ·

    Hi Jason, Like Mike said,

    Hi Jason,

     

    Like Mike said, never use FF relationships in a construction, installation or a working schedule. FS is the way to go.

    I'll only recommend use of FF & SS relationships when building a high-level schedule for

    1. Management reporting
    2. Integrating different contractors schedule
  4. 0
    Mike Testro ·

    Hi JasonBecause software

    Hi Jason

    Because software developers have never worked in construction.

    SS - FF links do have a place in manufacturing on a production line where a "ladder" system works well.

    Early MSP systems blocked FF links but they changed it in the latest versions.

    Best regards

    Mike Testro

  5. 0
    Vladimir Liberzon ·

    Hi Jason,we do not advise to

    Hi Jason,

    we do not advise to use negative lags but FF relationships are not rare in construction, especially in linear projects like road, pipeline and similar objects construction. Usually FF is used together with SS link (plus lag) with the same activities. These links usually reflect the requirement to keep certain distance between the crews that are doing consequent works.

  6. 0
    Zoltan Palffy ·

    agree never use a negative

    agree never use a negative lag. A lot of time scheduling specifications prohibits the use of negative lags. 