SChedule Behavior
- Created
- 3
- 2
In my (construction) programme (P6 v7) three Level of Effort activities in the second level of WBS are linked with the first activity “Commencement of the Project” with “SS” relationship and the last activity of the project “Project Completion Date” with “FF” relationship i.e. the whole project and showing a duration 610 days each the WBS summary also showing 610 days.
The calendar of these activities are “6 Days a Week”.
The activities related to the Client, Engineer, and the Local Authorities have “5 Day Work”
The engineering and procurement activities have “7 Day Work” calendar.
All the construction activities have “6 Days Work” calendar.
I could not understand this behavior of the schedule but I have to explain this to my Client’s planner, can anyone help me?
Cheers
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?