Primavera P6 V7.0 resource data export to xl

John DavisonMember for 11 years 10 months
Created
4
1
0

Hi Guys

Appologies if this is an old chestnut but I have just moved jobs and using P6 V7 for the first time.

Also new to this forum

I am struggling to get the resource allocation data out of P6 and into xls

Tried the wizard but still no joy

Could anyone point me in the right direction

Many Thanks

JD

4 replies

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi JohnGo to the  top left

    Hi John

    Go to the  top left side of your screen and seek "Resource assignments". Here you seen all the resource assingments . You can now filter for budgeted or remaining. Seclect, copy and past. This shoud do.

    Regards Johannes

  2. 0
    Zoltan Palffy ·

    look for my detailed

    look for my detailed instructions at the link below 

    its a deltailed pdf file

     

    http://pmsite.com/forums/viewthread/2840/

     

  3. 0
    Raymund de Laza ·

    John, As Johannes

    John, As Johannes suggestion... in Resource Assignment pane you can have a layout that shows all Resources with corresponding activities where it was assigned or the other way. regards,
  4. 0
    Zoltan Palffy ·

    look for my detailed

    look for my detailed instructions at the link below

    its a deltailed pdf file

     

    http://pmsite.com/forums/viewthread/2840/

Log in or join to reply