to display resources in the gant chart

Amar IadadenMember for 15 years 6 months
Created
2
3
0

I am a new user in primavera p6, please can some one to show me how to display on the gant chart the resources assigned for each activity beside the bar.

Thank you

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Amar,Copy the Resources into

    Amar,

    Copy the Resources into a UDF then use it as Bar Label.

     

    Regards,

  2. 0
    Zoltan Palffy ·

    that is incorrect you do not

    that is incorrect you do not need to make a udf 

    just go to the bars and select current bar labels 

    then click on the bar lables tab

    then select add 

    then in the position select right 

    clikc in the label area look in the drop down and select budget labor units for rmanhours or budget labor cost or whatever you want to show there