tracking physical % complete & % cost complete separately in the same project

Müjdat ÖzacarMember for 17 years 4 months
Created
1
3
0

Hi all,

When I track my physical progress i follow this way: after i assign resources to primavera(manhours and materials) i define 1$/h unit price for manhour resource so budgeted labor units gets equal to budgeted total cost . anyway when updating as per baseline i can track physical progress perfectly from earned value and performance % complete columns.
But now i wanna track also project cost complete in the same project %(as per Contract BOQ) separately in primavera including labor and material cost .. 
Is there any way to do it?

Thanks in advance

Mujdat Ozacar

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    you already have Budgted

    you already have Budgted total cost and Budgted Units 

    for your actual costs you can run a global change where actual costs equals Budgeted cost * % complete

    for actaul manhours you can run a global change where actual units equals Budgeted Units * % complete