tracking physical % complete & % cost complete separately in the same project
- Created
- 1
- 3
Hi all,
When I track my physical progress i follow this way: after i assign resources to primavera(manhours and materials) i define 1$/h unit price for manhour resource so budgeted labor units gets equal to budgeted total cost . anyway when updating as per baseline i can track physical progress perfectly from earned value and performance % complete columns.
But now i wanna track also project cost complete in the same project %(as per Contract BOQ) separately in primavera including labor and material cost ..
Is there any way to do it?
Thanks in advance