View roles & quantities required for future
- Created
- 1
- 2
Hi,
I have 3 projects which I have planned out, and assigned roles to the activities. What I am trying to get the P6 8.4 client to show me is a graph or just numbers of how many of each role we need for each month of the year. I have tried 'Activity Resource & Role Assignments' report and its halfway there, apart from if I need 3 of the same role at the same time it just repeats that information 3 times i.e.
Role Start Finish
Role 1 09-02-2015 - 28-03-15
Role 1 09-02-2015 - 28-03-15
Role 1 09-02-2015 - 28-03-15
Where as I am trying to get it to display the quantity required
Role 1 09-02-2015 - 28-03-15 x 3
Can anyone advise?
Thanks