Late Curves in an Updated Schedule
- Created
- 0
- 2
Need some help please!
I have been asked to generate late curves in an updated schedule. I am able to make it, however i have some observations that I think P6 release 8.3.2 is generating it incorrect. My understanding is that there should be no remaining cost/units for months earlier than DATA date if I am generating LATE curve. In case it generate, it should be as per ACTUAL. Please refer to the screenshot below. Upon investigation, i noticed that these remaining cost in months earlier than DATA date is due to the LEVEL of EFFORT activities which has LATE START equal to ACTUAL START for progressing activities (i think it should be at least equal to data date or earliest of the late date of its predecessors, correct me if I'm wrong).
I appreciate your assistance guys.
Cheers!
Ariel
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?