How to clear the "Unsatisfied Relationship" in schedule log?

Richard ChenMember for 11 years 9 months
Created
2
1
0

Hi all:

 

I am a planner from Taiwan, and in a Sabic project by now.

The client requested me to clear all the Unsatisfied Relationship in schedule log.

I tried many times by still can't find a logical way to clear it all.

THANKS FOR YOUR KINDLY HELP~

 

1. What is the definition of "Unsatisfied Relationship"?

2. How to clear it in schedule log?

2 replies

Oldest first
  1. 0
    Yanqing Gong ·

    Hi, Chen,I also encountered

    Hi, Chen,

    I also encountered this problem, and found that when I remove the "SS" relationship linked to the completed activity, the corresponding "Unsatisfied Relationship in schedule log" would disappear. You can have a try.Hope this can help you.

     

  2. 0
    Richard Chen ·

    Thanks Gong,I cleared some

    Thanks Gong,

    I cleared some "unsatisfied relationship" by your way.

     

    I found that A is predecessor and B is successor, A connects to B with FF relationship.

    IF B has a actual start, the FF relationship will be defined as "unsatisfied relationship".

    Only I can do is to remove the relationship or change the relationship to SS.