Substantial Completion Date Change
In the Open Standard
Gerardo CisnerosMember for 11 years 7 months
- Created
- 1
- 3
0
Currently I'm working on a project where I review a subcontractor's P6 schedule and implement their update when I submit mine to the client. When I import their project into my machine, I hit re-calculate and their Substantial Completion date changes by a day from what they report. I do not make any changes to their schedule. I simply import and recalculate. All other dates remain the same except for a few other high level milestones which in all cases move up a day. Any ideas to why this happens?
Their schedule does have multiple calendars, some that are global and others that are project. I was wondering if maybe the issue is in the global calendars but I did a fresh import into another machine that did not have existing global calendars and the same issue arose.
Any ideas will be much appreciated.
Thanks,
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?