What is the best way to compare 2 schedules?

John DrokovicMember for 17 years
Created
1
2
0

I want to find out what relationships have been added / deleted from a previous schedule. What is the best (or fastest) way of doing this automatically, without having to review them one by one, visually, manually, etc.?

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    you have several choices you

    you have several choices you can compare the log file between the two projects and look at the statistics or use claim digger or you can use a third party program to do this such as schedule analyzer enterprise