Spot the difference in two Primavera update

Amjad HananMember for 11 years 9 months
Created
6
2
0

Dear Gents, 

We used to send primavera update to our planning manager on weekly basis. Is there any provision in primavera to spot the difference in progress for the only activities from the previous week.   

Your help in this concern is unfathomable! 

6 replies

Oldest first
  1. 0
    Kannan CP ·

    Amjad,Set the last week

    Amjad,

    Set the last week project as the baseline for this week update. Create the filter to show the baseline dates for the previous week. compare it against the present update.

    I hope this will help

  2. 0
    Zoltan Palffy ·

    why not use claim digger ?

    why not use claim digger ?

  3. 0
    Zoltan Palffy ·

    why not use claim digger ?

    why not use claim digger ?

  4. 0
    Eoin Flannery ·

    +1 for using baselines.We

    +1 for using baselines.

    We would use an original baseline to display the Rev0 then use a second bassline as a copy of the previous weeks issue.

    A trick we use is to save each weekly issue as a baseline (witht the issue date) but dont have it displayed.

    So in essence we have 3 "live" basleine with each issue.

    1: Original Rev 0

    2: Last weeks basline

    3: Copy of issue (not displayed)

     

    Each week we issue the shcedule we would simply change the copy of last weeks baseline.

  5. 0
    Amjad Hanan ·

    Thank you Mr. Kannan and Mr.

    Thank you Mr. Kannan and Mr. Eoin , It works! 

     

    @Zoltan, Is claim digger an add-in option in primavera? When I select claim Digger, it retrieve a mesage "The selected application: C:\Program Files (x86)\Java\jre7\bin\javaw.exe cannot be found." have experineced any issue as such ?

     

  6. 0
    Zoltan Palffy ·

    it appears that you do not

    it appears that you do not have java either installed or enabled 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?