Skip to content

Ahead of Schedule Activities

Hafiz Khalid HussainMember for 14 years 4 months
Created
4
1
0

Hi guys,

My project is in the middle and i have some activities completed, mostly activities status is in progress. Some body help me on:

1) I want number of in progress activities that are ahead of the schedule.

2) Number of in progress activities that are behind the schedule.

3) Number of in progress activities that are on schedule.

Some one tell me the filter for above listed requirement

 

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    1st add a column for number

    1st add a column for number of activities its under number of activities then select activity count

    then under group and sort check show group totals and show grand totals

    you must maintain and assign a baseline

    then filter #1 activities ahead of ahead of schedule 

    ANY

    where start is less than variance BL project start

    or 

    where finish is less than variance BL project finish

    filter #2 behind schedule 

    where start is greater than variance BL project start

    or 

    where finish is greater than variance BL project finish

    filter #3

    where start is equal to variance BL project start

    or 

    where finish is equal to variance BL project finish

     

    another way

    filter #1

    total float is greater than 0

    filter #2

    total float is less than 0

    filter #3

    total float equal 0

     

    but I suspect you want the first set of parameters 

     

  2. 0
    Hafiz Khalid Hussain ·

    Dear Zoltan,Thx for your

    Dear Zoltan,

    Thx for your concern, but i check your method and "Variance BL Project Start" is not available in filters. Actually it is available in "parameters" but not under "value". Kindly further guid

  3. 0
    Zoltan Palffy ·

    sorry did it off the top of

    sorry did it off the top of my head

    here it is 

    then filter #1 activities ahead of ahead of schedule 

    ANY

    where variance BL project start is less than start 

    or 

    where variance BL project finish is less than finish 

    filter #2 behind schedule 

    where variance BL project start is greater than start 

    or 

    where variance BL project finish if greater than finish 

    filter #3

    where variance BL project start is equal to start

    or 

    where variance BL project finish is equal to finish

  4. 0
    Sunil Babu ·

    Hi Hafiz,Also you can check,

    Hi Hafiz,

    Also you can check, variance with BL finish dates. Activities with -ve values indicates behind schedule and those having +ve indicates ahead of schedule.

    Best Regards,

    Sunil.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?