Changing resorce type
- Created
- 5
- 2
Afternoon all :)
I have a P6 v8.4 programme in which a material resource has been used to generate cost. as we are working ot an activity schedule, all costs have to be allocated at the finish of the task.
My problem is that any time th eduration varies, the cost varies accordingly due to the duration changing. I nd this cost to remain constant regardless o fchanges to duration. The client will not permit expenses (which would be simple to use) which does complicate it a bit for me. I can create a non material resource that remains constant, but this would invlove changing all resources in the programme (about 8 or 900 of them) which is not feasible on an individual level.
The project is set to not update units when costs change, not recalculate actual units and cost when duration changes, an in resources I have tried with "calculate costs from units) checked and unchecked. None of these help.
Is it possible to set a material cost so that it will not vary in cost regardless of duration change, and what settings would I need to use? Failing that. is it possible to swap a material resource with a non material one, bearing in mind that I have some actual values?
thans in advance, if you need more info I will get back as soon as I can.
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?