Seeking the way to define Progress Measuring Method in Primavera P6
In the Open Standard
Irfan KhanMember for 17 years 3 months
- Created
- 1
- 5
0
Hi to all,
I have got new project & the project's scope is to rectify & renovate the Buildings.
Here my Baseline schedule has been approved as per given Finish milestones by client & i loaded appropriate Manhours upon my experience because there is no any Bill of Quantity & Unit Rates, furthermore i dont have rates for applying the correct Manhours for Demolition/Rectification therefore based on experience i reached at destination.
Now whenever i am showing my progress as per Earned Manhours to client so they are objecting & they are not happy with my Overall Actual Progress %, According to me its 26.50% & according to client its 15.00%.
Now in the meeting client asked that measure your progress based on Duration & here is the question that how to measure the Overall progress based on Duration ?
Do anyone advise me that how to measure overall progress based on Duration ?
Thanks in advance...... :)
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?