deadline column

Ahmet TuterMember for 13 years 8 months
Created
2
2
0

i am able to put in a date value to deadline column but it does not seem to affect any floats or finsih dates. how does this deadline colmun work?

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    the forward and backward

    the forward and backward passes  along with the calendar, logic, durations and constraints determine the dates. There is no such thing as a deadline date column unless you created it yourself. It is not a standard column.

  2. 0
    Ahmet Tuter ·

    i did not create it myself. i

    i did not create it myself. i am using 8.4 version of p6. it was a standard column. can anybody help?