Hello All , I'm new Here ,Also I'm new in Primavera

Can Anyone help me to understand these terms:

1- Budgeted unit / time

2- Budgeted Units

3- Price /Unit

4- BUdgeted Cost

 Thanks in Advance And Best Regards..........

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    1. Budget unit/time = how

    1. Budget unit/time = how many units that you expect to use per day 8 hours/day = 1 man or 16 hours /time is 2 men per day 

    2. Budget Units = Original planned amount of Manhours or Material of units or what ever it is that you are tracking linear feet of conduit. Cubic Yards of Concrete

    3. Price /Unit is the price per one unit of what ever it is that you are tracking like one apple $.50 and 2 apples = $1.00

    put in the units and the total price is calculated by multiplying the price /unit times the number of units.

    4. Budget costs = your original budget cost to perform this activity. 