Level activities with small duration (<1 hour)

Berb CristianMember for 11 years 2 months
Created
3
1
0

Hi,

I have this situation:

Duration activities are  1 hour in level activities to share (corect) resources

 

Duration activities are  30 min ; in level activities to share resources ; incorect results.

P6 dont level activities with small duration (minutes) ?

Thanks

3 replies

Oldest first
  1. 0
    Mahisha M. Reno ·

    Hi, You might want to look at

    Hi,

     

    You might want to look at the "Max unit / time" on the resource which assigned to those activities.

    See if the max unit/time still allow the resource to be executed on the same hour or not..

     

    Regard,

    MRE

  2. 0
    Zoltan Palffy ·

    check your resource calendar

    check your resource calendar also 

  3. 0
    Rafael Davila ·

    Any software should handle

    Any software should handle resource leveling down to the minimum duration you can assign to an activity, you got to be missing something. I do not use P6 but see it can display 1/100 minutes.

    Try checking Activity Duration Type.

    http://www.qsarticle.com/activity-duration-types-in-primavera-project-planner-p6/

    If the above does not works then I suggest trying with the following simple schedule from scratch and see what happens. One resource A and one resource B units are available. There are no activity links, very simple. Even if one second activities it should do it.

    ShortDurations photo ShortDurations_zpsrbh6isul.jpg

    Good luck.