Level Of Effort Spurious Actuals ?

Alastair MorrisonMember for 19 years 8 months
Created
3
1
0

Can anyone shed some light on why occasionaly and randmly all my summary level of effort tasks show an actual start and an actual finish when they have no physical progress  recorded and none of the tasks they are spanning have actuals?  They all have logic of SS and FF so the point that level of effort tasks will show 100% complete if no logic is applied does not count in this instance.  Any advice help would be appreciated.

3 replies

Oldest first
  1. 0
    Alastair Morrison ·

    This would appear to be my

    This would appear to be my issue one of the planners must have the "ignore relationships to and from other projects" ticked in there schedule options.

    Therefore when they schedule their Lv3 plan with the summary / control plan Primavera does as it's told and ignores the links and the LoE's activities which have drivers from the other Lv3's go to zero remaining duration. 

  2. 0
    Zoltan Palffy ·

    so the lesson learned here

    so the lesson learned here was to remember not to ignore relationships to and from other porjects

  3. 0
    Alastair Morrison ·

    Exactly !!!  Make surte the

    Exactly !!!  Make surte the "ignore other projects " box is   unticked in the scheduleing options