Display Activity Code values in schedule only, not "empty" bands

David BallMember for 19 years 2 months
Created
2
3
0

Hi,

I have 5 Activity Codes assigned to the activities in my schedule and these are all included in the Group By column of the Group and Sort window. The last Code is “Discipline” and one of it values is “Cable”.

Within the Cable node in the schedule I want to have a further level with values of “Install”, “Terminate” and “Test”.

The problem I have is that when I create the new code, “Phase”, and assign these codes to the cable activities and include the new code in the Group By column of Group and Sort I get “No Phase” displayed within every node, except “Cable”, which has the headings Install, Terminate and Test, as expected.

I have checked the “Hide if Empty” box in Group and Sort but still get the same thing.

Is there any way to show this new code for Cable only?

 

Thanks very much

 

Dave

2 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Hi,Create a Filter such as

    Hi,

    Create a Filter such as the Code is equal to Phase.

  2. 0
    Gary Whitehead ·

    Rather than using a new phase

    Rather than using a new phase code, I think you're probably best of adding install, terminate & test as 3 new values in the discipline code, indented to be children of the existing cable value.

    Make sure you also indent the discipline code in your group & sort settings

     

     

     
     
     
     