Actuals given,activiy %=100 but there are few remaining units in resources shown

karthikeyan VMember for 11 years 1 month
Created
1
2
0

Hi,

In an already existing program, I tried to give a finish date for an activity.

However, it takes start date as finish date.

Upon completely moving out the start date & finish date & then trying to re-enter both of them, it accepts and shows activity %=100

HOwever,in the resources, there seem to be remaining units still left out instead of zero.

Kindly advise.

Thanks

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    at the activity level in the

    at the activity level in the resource tab right click an choose Customize Resource Column and expand the General category

    on the left hand side check auto compute actuals and bring it to the right hand side 

    make sure that this box is checked. 