P6 EPPM Actuals Dissapeared

Norman BMember for 11 years 2 months
Created
1
3
0

Hello all, 

Something bizarre is happening with my P6 project. I am using P6 EPPM, and I was making forecast cost updates. Once i was done with my updates, I noticed all my non-labour actuals had dissapeared. I contacted one of our support guys, who could see all the actuals, and I refreshed my screen and all the actuals suddenly re-appeared. But then I noticed by ETC went wrong. So I ran "Recalculate Assignment Costs" which corrected my ETC but my non-labour actuals dissapeared again. 

Not too sure what is going on. 

Any help is appreciated. 

Thanks

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    hard to tell not knowing your

    hard to tell not knowing your settings for 

    what is your duration type ?

    what is your % complete type ?

    what is you activity type ? 

    how you are updating actual units or costs do you reset Original duraiton and units to remaining ? or do you reset remaing duraiton and units to original ?

    are you using store period perforamnce ?

Log in or join to reply