Importing actual progress in a schedule

Kannan CPMember for 18 years 4 months
Created
10
5
0

Dear All,

Due to a variation order, the approved baseline programme has been revised with the incorporation of the variation item and few changes in the logic as mitigation.

In the last updated programme (without variation), out of 11,000 activities nearly 5000 activities are completed/in progress.

In order to set the revised baseline, is there any option to import the progress of those 5000 activities- from the last updated schedule to the revissed baseline?

Thanks

 

Best Regards

Kannan

10 replies

Oldest first
  1. 0
    Raymund de Laza ·

    I suggest to use the Update

    I suggest to use the Update Baseline feature in the Maintain Baseline Window.

  2. 0
    Steve Eiden ·

    Its a bit complicated but i

    Its a bit complicated but i import AS/AF and % into p6 frequently.The key is to correlate in Excel the list of actual dates by ID (i use vlookup) so that the rows of updated tasks line up by ID with the rows in the xls export from the baseline file. Then i make sure all AS/AF dates are 0800 to 1700 and then I import...works like a charm. This method maintains the WBS codes for all the tasks involved.
  3. 0
    Zoltan Palffy ·

    I also do as Steve does the

    I also do as Steve does the key is to export the excel file with the correct columns and then use this as a template for populating and importing back into P6. The TIMES must be correct with the actual start and finish dates. 

  4. 0
    Robin Clare-Talbot ·

    Hi all,Raymund has the best

    Hi all,

    Raymund has the best suggestion on this. Since they have improved this module in the last 2 revisions, the Baseline Update is a fantastic way to get around some tedious tasks.

    I would suggest however, until you are 100% familiar with all the options you have in the Baseline Update, make a backup of your schedule, and try a few things out first.

    We have done baseline update on schedules over 100,000 activities, it may seem like your machine, the server and all things Primavera have frozen, but be patient, give it time and it will work.

  5. 0
    Kannan CP ·

    Thanks all.. Best

    Thanks all..

     

    Best Regards

    Kannan

  6. 0
    Mohammed Ayaz Maniar ·

    Hi All. Can anyone guide me

    Hi All. Can anyone guide me how to import actual start / actual finish, physical percent complete and duration percent complete from Excel, as I need to transfer actuals from other schedule into revised schedule by excel. Regards, Mohammed Ayaz
  7. 0
    Mohammed Ayaz Maniar ·

    Hi All. Can anyone guide me

    Hi All. Can anyone guide me how to import actual start / actual finish, physical percent complete and duration percent complete from Excel, as I need to transfer actuals from other schedule into revised schedule by excel. Regards, Mohammed Ayaz
  8. 0
    Mohammed Ayaz Maniar ·

    Hi All. Can anyone guide me

    Hi All. Can anyone guide me how to import actual start / actual finish, physical percent complete and duration percent complete from Excel, as I need to transfer actuals from other schedule into revised schedule by excel. Regards, Mohammed Ayaz
  9. 0
    Anas Khan ·

    Steve.I have two programs.1)

    Steve.

    I have two programs.

    1) original baseline.

    2) substantial completion mep program.

    What i have to do is, import resources and budgeted labor units from (2) to (1), but when i do this, it does not happen.

    I think as they are two different programs, i will have to map the WBS(es) as well.

    Can you help me out with this issue?

  10. 0
    Zoltan Palffy ·

    make sure that the actual

    make sure that the actual start TIME an and actual finish TIME is correct