Importing actual progress in a schedule
In the Open Standard
Kannan CPMember for 18 years 4 months
- Created
- 10
- 5
0
Dear All,
Due to a variation order, the approved baseline programme has been revised with the incorporation of the variation item and few changes in the logic as mitigation.
In the last updated programme (without variation), out of 11,000 activities nearly 5000 activities are completed/in progress.
In order to set the revised baseline, is there any option to import the progress of those 5000 activities- from the last updated schedule to the revissed baseline?
Thanks
Best Regards
Kannan
10 replies