Migrating from P3 to P6

Wadi El-Din HammoudaMember for 12 years 3 months
Created
1
2
0

Hello,

I do have a problem migrating from P3 to P6. Everything seems fine except that the total float on the migrated schedule on P6 is 1 day less than the total float on the the original schedule on P3.

Did anyone have such problem before?! Can anyone help?!

Thanks in advance,

Wadi

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    p3 does not specifically use

    p3 does not specifically use TIMES and P6 does go to edit users preferences 

    click on the dates tab

    at the bottom select Time 12 hours

    now go to the projects directory and make sure that your project is highlighted

    click on the dates tab

    click in the planned start make sure that your TIME is 8:00 am or whatever the earliest hours is in your calendar

    click in the must fnish by date and change the TIME to 5:00 pm or what every the latest hour is in your calendar 

    click in the data date and make the TIME 8:00 am or whatever the earliest hours is in your calendar

    go to your activities filter for any constraints

    for ALL start type of constraints make the TIME 8:00 am or whatever the earliest hours is in your calendar

    for all finish type constraints make the TIME 5:00 pm or what every the latest hour is in your calendar 

    schedule the project F9 make sure the TIME is 8:00 am or whatever the earliest hours is in your calendar

    also check your calendar amd make sure that the start TIMES and finish TIMES for each day is correct.

Log in or join to reply