P6 Schedule

Gregg StrumpfMember for 10 years 10 months
Created
2
1
0

When i am ready to print my schedule in print preview the gantt chart portion of the schedule goes to year 2012 even though my schedule has correct dates on it which i view on the screen but when i click print preview and print out it goes back to 2012 with nothing on it? 

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Greg,open the page setup

    Hi Greg,

    open the page setup dialog and display the "Options" tab (far right); then select the correct Start and Finish dates for the print

    Alexandre

  2. 0
    Gregg Strumpf ·

    Thank you very much..that did

    Thank you very much..that did it

Log in or join to reply