Labor units

Abilash Palakkadan MathewMember for 14 years 1 month
Created
1
1
0
Hi, When I'm assigning resources on activities the entrie unit is appearing on the first day itself. I mean an activity with 10 days duration when assignning 1000 labor units it should equally distribute during the working days. If it is seven day working calendar then it should be 100 units / day. But in my case it is appearing 1000 units on the first day and 0 units on the remaining 9days. Can anyone help me fix this problem. By Abilash

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    there are 2

    there are 2 possibilities

    Possibility #1 

    this resource is on a LOE activity type.If this is the case then assign a curve to the resource

     

    Possibility #2

    on the resource the default units/day is set to 0. If this is the case change the default units/day on the resource to 8. 

Log in or join to reply