P6 Calendar deletion
- Created
- 2
- 3
I have an issue with deleting one specific Global Calendar. When I check to see what project is using the Calendar, nothing shows up, and the same goes for resources. When I try to delete to calendar I get a message saying it cannot be deleted because it is being used by a project. My question is how do I find out what project (or baseline) is using the calendar whether it be the calendar itself or as a reference for the project specific calendar.
I am no good at report writing with P6 but if there is a report that would help, please do share with me.
Thank you for your time.