Total Float Variance Between Current and Baseline Schedules
In the Open Standard
John MolMember for 10 years 9 months
- Created
- 3
- 3
0
P3 had the ability to include a report column that provided the Total Float Variance between two schedules (typically the current update and its baseline). However, I've not been able to recreate this variance report in P6 v8.2. My intuitioin tells me that I can include a column which provides the variance between the Late Finish dates. However, I'm not confadent that these two reports provide the exact results.
Does anyone know how to create a column which provides the Total Float Variance between a current update and its baseline?
Thank you!
3 replies