Hi all,
Im a junior planner who is working on numerous projects that have been built by somebody else. I have a few questions if any body could help me.
The project went live last monday and i updated on friday when i update the physical% complete and F9 it it doesnt change the remaining duration on the activity should this be done manually? or should i add another column for activity % complete and do it that way? When i update the histo in excel it goes on the man hours that is generated in the resource usage spreadsheet, these are all generated for the forthcoming weeks if i change the remaing duration maually will this have any effect to the forth coming weeks.
in the same project i know there is part of the critical path ment to start on monday but i know it wont start till after that date when i F9 iton friday my end date will obviousley push out is there any way of pulling this end date back? say by reducing the hours that they have budgeted for this activity which i think has been over budgeted?.
im realitivly new to this so i appologise if my questions are a bit simple.
any help would be most appreciated.
Kind Regards
L8s
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?