Hi All,
There is earned value adjustment shall be done in case Of Finishing the activity less than BAC.
Let me clarify the case with Negative impacts:
Act A1000 BAC =1,000,000 U.S.D ACT ST 01-DEC-15 ACT FS 30-DEC-15 Finished at 500,000 U.S.D
Options:
1- Update 100% and actual dates -impact showing EV=1,000,000 INSTEAD OF 500,000
2- Update 50% ,actual start and ETC=0 - Impact Showing the activity in progress while in reality it has been finished
3- Update 100% with actual dates and add new activity with -500,000 to B.L then
update -Impact BAC will change from 1,000,000 to 500,000 which not correct
I’m convinced with option 1 while my superior convinced with option 3 and I’m trying to convince
Please advise about the proper one and if there is any other option?
Thanks
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?