Automacally Allow ressources!!
- Created
- 9
- 4
Hii every body!!!
i want to create a new projet on P6 but i have un probleme: i want to know how to make activity automatically started only when one between 3 ressources is available?
For exemple:
I have 3 teams: T1, T2 and T3.
I have 5 activities whith duration in brackets : A1 (3days), A2(3d), A3(3d), A4(4d) ,A5 (2d).
To A1 i assign T1. one day after start A1 i start A2 with T2. One day after A2, i start A3 with T3.
I notice now that i don't have any team available so i want that if i plan A4 starting at the same day with A3, P6 should refuse and tell me that i can only start it the next day (at the end of A1 when T1 would be available).
If there is 1 team available, P6 automacally assign that team to the activity.
If there is 2 teams, P6 presents those two teams and i select one of them.
same thing for 3 teams.
Thank you for your answes.
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?