Total float in decimals, multiple calendars
In the Open Standard
Bhajan ChandrasekharanMember for 15 years 11 months
- Created
- 7
- 5
0
Hi all, I'm developing a baseline and I'm seeing TF in decimals (example 10.5) for activities assigned with one particular calendar(6 day workweek, 20h/day, 02:00 to 22:00). My other calendars are: 7 day workweek, 10h/day, 12:00 to 22:00 and 5 day workweek, 10h/day, 12:00 to 22:00.
Data date is start of first acitvity 3 Feb 2016, 12:00 because this activity is assigned with the 3rd calendar(5 day workweek, 10h/day, 12:00 to 22:00). Am I missing something?
Thanks.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?