Assigning baseline
In the Open Standard
Ketaki AlurkarMember for 10 years 8 months
- Created
- 3
- 2
0
I have a question about assigning baselines each time I am updating. For the projects that I am working on I have to assign he final baseline for each month's schedule update. Is there any way to assign the baseline for the project and not have to add from maintain baseline and assign baseline for each update. I know that once it's assigned it stays there. But I have to export the updated schedule to client and once approved by them have to import it again and start over with next month's update which makes me lose the baseline.