Schedule run
In the Open Standard
Vigeeth SalianMember for 10 years 7 months
- Created
- 2
- 1
0
Hi guys,
I am in big problem.
i my project is in initial stage.
i have Finished linking but when i run schedule ,Latest Early Finish Date pushed one month behind.Plz help me out.
Planned start is 2march 2016 and finish is 29march 2018
after inserting current data date in schedule as 2march 2016 my finish is 13 feb 2018.
what should i do?