unit % Complete ( attachments )

Aejaz Ahmed AhmedMember for 12 years 6 months
Created
3
1
0

Hi Guys

i want to know about unit % Complete.in my programm Activities window shows 1.68% whereas Resourece assignment  shows 2.23%.whats wrong in my programm?

i attached following pics.

can you explain me details.

Pic-01

Pic-02

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Hard to tell can not see the

    Hard to tell can not see the pics

    1. Is the activity type task dependent or resource dependent ?

    2. What are you using for duration type ? 

    3. What are you using for % Complete type ?

    4. Under Calcluations do you have Link Actual and actual this period units and costs checked

    5. Under Calculations do you have Replace Actual Units and Costs When duration % complete changes ?

  2. 0
    Aejaz Ahmed Ahmed ·

    A-1 type task dependentA-2

    A-1 type task dependent

    A-2 Fixed Duration & Units

    A-3 Physical % complete

    A-4 & A-5 i used default setting.

  3. 0
    Zoltan Palffy ·

    run a global change make sure

    run a global change make sure that 

    where activity status is not equal to comeplete 

    then duraiton % complete = physcial % ciomplete 

Log in or join to reply